LANSARY. Nuclear Bring us the decision
Why now — nuclear

The money funding the next decade also re-prices what you must prove.

An ~£38bn nuclear new build at Sizewell C and Britain’s first SMR fleet are running the nuclear supply base toward full stretch, while the fuel, the forgings, the regulator and the skills pool all move at once. The demand is real, and so is the bar that comes with it. Below: the nine dated changes already in the record, newest first, and the specific exposure each one puts on you. Not a forecast — what has already happened.

The ground that moved

Nine dated changes. Each one puts something specific at risk.

13 Apr 2026
Britain’s first SMR fleet went to contract — one vendor, one site.

On 13 April 2026 Great British Energy–Nuclear and Rolls-Royce SMR signed a contract to begin delivery of three small modular reactors (at least 1.4GWe combined), enabled by the over £2.5bn allocated to the SMR programme in the 2025 Spending Review — an allocation to enable this contract and wider delivery, not the contract value, which neither party discloses — with the National Wealth Fund committing up to £599m to Rolls-Royce SMR. The UK’s first SMR fleet now concentrates on a single OEM prime at a single site (Wylfa, Anglesey, per the Rolls-Royce release), so any SMR supply-chain exposure you carry funnels onto one vendor and one location with no second-source fallback.

20 Feb 2026
Hinkley Point C slipped to 2030 at £35bn — the EPR schedule risk your reference design inherits.

In its 2025 annual results (20 February 2026) EDF adjusted the start of production by Hinkley Point C Unit 1 to 2030 and estimated the completion cost at £35bn in 2015 sterling — EDF’s own project-cost estimate stated in 2015 money (a single point figure, not the third-party £43–£48bn current-price conversions), driven by a 12-month commissioning delay in the electromechanical work, which EDF states would add roughly £1bn (2015 sterling) per further 12-month slip. A UK nuclear buyer inherits single-vendor EPR dependency on EDF/Framatome — the same reference design and expertise now transferred into Sizewell C — with the electromechanical work as the current schedule-critical single point of failure on your own timeline.

24 Nov 2025
Nuclear regulation is being rebuilt — 47 recommendations, and the deciding regulator in flux.

On 24 November 2025 the Nuclear Regulatory Taskforce (a joint DESNZ / Ministry of Defence review) published its final report, the Nuclear Regulatory Review 2025, making 47 recommendations — including a single Commission on Nuclear Regulation and merging the Defence Nuclear Safety Regulator into the ONR. It is a recommendations review the government accepted in principle at the Budget and formally responded to (“Building our nuclear nation”) on 13 March 2026 — not law in force, and not committed spend. A developer’s or supplier’s regulatory pathway — GDA, permitting, the lead-regulator model and the ONR/DNSR consolidation — is being restructured on a 2026–2028 timetable, so approval timelines and the identity of the deciding regulator are a live sourcing and schedule risk you carry into any UK new-build or SMR commitment.

07 Nov 2025
China’s rare-earth and magnet controls were suspended for a year — not repealed.

On 7 November 2025 China’s Ministry of Commerce and the General Administration of Customs issued Announcement No. 70, suspending — not repealing — the six rare-earth and permanent-magnet export-control measures of 9 October 2025, including the extraterritorial trigger that reaches any foreign item whose Chinese-origin rare earths are 0.1% of its value, through 10 November 2026. The Chinese text suspends implementation; the enabling Export Control Law stays in force, and MOFCOM speaks only of continued discussions on what follows — so re-arming from 11 November 2026 is a supported inference, not a stated policy. The dependency under every NdFeB permanent magnet in a reactor-coolant-pump motor or safety-valve actuator never left — only its enforcement is paused, and it is your own exposure to carry.

22 Jul 2025
Buying into the nuclear supply chain became a mandatory-notification transaction.

The UK’s fourth National Security and Investment Act annual report (Cabinet Office, 22 July 2025, covering 1 April 2024 – 31 March 2025) recorded 1,143 notifications, 56 call-in notices and 17 final orders, with Energy third by final orders (5 of 17) — though Energy is not a top-three sector by notifications, and the report publishes no nuclear-specific figure. But “Civil Nuclear” is one of the 17 mandatory sensitive sectors under the Notifiable Acquisition Regulations 2021 — a statutory scope fact, not a spend figure. A change of control over a UK SMR developer, fuel-cycle, reactor-technology or supply-chain business is a mandatory-notification transaction: it faces Cabinet Office screening, potential call-in and conditions or an unwinding order, with completion void until cleared.

15 May 2024
The skilled-person pool has to roughly double this decade — 40,000 new jobs by 2030.

The National Nuclear Strategic Plan for Skills, launched by the Nuclear Skills Taskforce on 15 May 2024, sets the ambition to fill 40,000 new nuclear jobs by 2030 — doubling the current rate of recruitment across the civil and defence nuclear sectors; the workforce, estimated at around 83,000 in 2023, is modelled by the Nuclear Skills Delivery Group from industry forecasts to need around 120,000 by the early 2030s. It is a forecast and an ambition, not committed spend. Any UK nuclear programme you touch — SMR, new-build, naval — is schedule- and cost-gated on a SQEP pool that must roughly double, a structural scarcity that inflates skilled-labour cost and delivery risk across your own timeline.

08 May 2024
Advanced-fuel supply runs through one state supplier until a UK plant produces around 2031.

On 8 May 2024 the government awarded £196m to Urenco — committed award money, part of a £300m HALEU programme — to build a High-Assay Low-Enriched Uranium enrichment facility at Capenhurst, Cheshire, targeting up to 10 tonnes of HALEU per year by 2031 (a project target) to end Russia’s position as the world’s only commercial HALEU producer, in a market where Russia holds 40% of global enrichment capacity (IEA, January 2025). A UK or European operator’s enriched-uranium — and specifically HALEU — supply is exposed to one state-controlled supplier, Rosatom, holding around 40% of world enrichment capacity and, until Capenhurst reaches production around 2031, the only commercial HALEU source. Any advanced or SMR fuel plan carries that single-country dependency until then — your own fuel exposure.

31 Mar 2022
RAB financing put your supply-chain revenue on a regulated consumer stream during construction.

The Nuclear Energy (Financing) Act 2022 (Royal Assent 31 March 2022) established the Regulated Asset Base model for funding new UK nuclear projects, under which revenue is collected from electricity suppliers by the Low Carbon Contracts Company — a regulated-revenue financing framework, not a committed spend, equity stake or project-cost figure — and Sizewell C is the first project financed on this model (per DESNZ). Under RAB, a developer’s or supplier’s supply chain is paid from a regulated, Ofgem-overseen consumer-funded revenue stream during construction, so suppliers are exposed to Ofgem cost-allowance decisions and the Special Administration Regime, not just to a single EPC counterparty’s balance sheet.

19 Aug 2021
The largest reactor forgings run through a global handful of forgemasters — and the UK’s only integrated high-integrity house is now state-owned.

In 2021 (offer launched 28 July, completed 19 August) the UK Ministry of Defence acquired Sheffield Forgemasters — in the government’s own words “the only available manufacturer with the skills and capability to produce large scale high-integrity castings and forgings from specialist steels in an integrated facility” for critical UK programmes — for £2.56m of share capital plus assumed debt, with up to £400m of planned investment over 10 years (a forward-investment ceiling, not committed spend). Globally, ultra-large reactor-pressure-vessel forgings are made by only a handful of forgemasters — Japan Steel Works, which claims around 80% of the world market for large forged nuclear components (a company-attributed claim, not independently audited), plus China First Heavy Industries, Doosan and a few others — each on 14,000–16,500-tonne presses. Any UK nuclear or naval-reactor programme sits behind a single domestic forgemaster and, for the largest civil RPV forgings, behind a global handful on multi-year single-line lead times — a concentrated, long-lead single-source chokepoint you inherit.

Each of these maps to a nuclear decision you can put to us — settled against one published standard, delivered as an Evidence Pack. See the nine Evidence Packs →

Sources: GOV.UK / DESNZ, “Great British Energy–Nuclear and Rolls-Royce SMR sign contract” (13 Apr 2026), corroborated by Rolls-Royce official release; EDF (Groupe EDF), 2025 Annual Results (20 Feb 2026); GOV.UK / DESNZ & Ministry of Defence, Nuclear Regulatory Taskforce — “Nuclear Regulatory Review 2025” (24 Nov 2025), government response “Building our nuclear nation” (13 Mar 2026); MOFCOM (China) & General Administration of Customs, Announcement No. 70 of 2025 (7 Nov 2025), with Announcement No. 61 for the 0.1% trigger and Export Control Law basis; Cabinet Office, National Security and Investment Act 2021 Annual Report 2024-25 (22 Jul 2025), with the Notifiable Acquisition (Specification of Qualifying Entities) Regulations 2021 for Civil Nuclear scope; National Nuclear Strategic Plan for Skills, Nuclear Skills Taskforce (15 May 2024), cross-checked to DESNZ “Assessment of the clean energy skills challenge” (25 Mar 2025); GOV.UK / DESNZ, “UK first in Europe to invest in next generation of nuclear fuel” (Urenco £196m HALEU award, 8 May 2024) with IEA, “The Path to a New Era for Nuclear Energy” (16 Jan 2025) for Russia’s 40% enrichment-capacity share; legislation.gov.uk, Nuclear Energy (Financing) Act 2022 (c.15, Royal Assent 31 Mar 2022) with GOV.UK / DESNZ “Sizewell C: Regulated Asset Base (RAB)” (22 Jul 2025); GOV.UK / MOD, “UK government to acquire Sheffield Forgemasters International Limited” (offer 28 Jul 2021, completion 19 Aug 2021), with World Nuclear Association “Heavy Manufacturing of Power Plants” as stepping-stone for the JSW self-claimed ~80% global forging share. Every dated figure traces to a primary or official record.

Engage

One of these is already on your desk.

Bring it. We’ll tell you whether it’s a question we can settle, and to what grade — before you commit a bid, a build commitment, or a deal to it.