Civil nuclear · Global report · 1950–2050 · Reviewed 2026-07-13

The nuclear renaissance is real. The construction map is not evenly shared.

Policy support has broadened, construction remains concentrated, and repeat delivery exists in only a small number of programmes. Status discipline separates the live build from the wider pipeline.S01

This report separates ambition from achieved delivery so that a buyer can see which programme merits pursuit now and which public proof is still missing.

The policy map is not the construction maphero_schematic
The policy map is not the construction mapA national target, a named proposal, a reactor under construction and a unit in commercial operation prove different things.At a glance, the live build is…01Policy, licence, finance, first…02The strategic unit is successive…03Western re-entry spans completion…01The decisive test through the early…02

A national target, a named proposal, a reactor under construction and a unit in commercial operation prove different things.

The nuclear renaissance is real.…
administrative snapshot · 12 July 2026
77 reactors
under construction worldwideS01
The dated PRIS stock proves that the current cycle has moved beyond policy and proposal.
calculated from frozen PRIS unit records
49.49%
of construction capacity in ChinaS01
The share shows where the live build’s centre of gravity sits on a common net-capacity basis.
conditional modelled scenarios · 2050
1 of 4
NEA cases exceeds triplingS07S08
Only the most demanding scenario reaches the objective, tying the endpoint to an execution-system transformation.

Read this in 90 seconds

  1. At a glance, the live build is substantial but concentrated: PRIS listed 77 reactors and 80.720 GWe net under construction, with China holding roughly half by both measures. A real construction stock supports the renaissance claim, while its geography identifies where fleet-scale delivery is already happening.S01
  2. Policy, licence, finance, first concrete, first grid and commercial operation occur on different clocks and prove different things. A capacity target or even a licensed project cannot be counted as delivered power before it crosses the missing dated stages.S02S14S15S16
  3. The strategic unit is successive commercial delivery, not one completion or a repeat label assumed to shorten every schedule. Several completed units demonstrate institutions and supply chains continuing; schedule improvement still has to be observed rather than presumed.S03S09S22
  4. Western re-entry spans completion, restart licensing, SMR construction, large-reactor construction, FID and connected trial rather than one uniform new-build wave. Each status presents a different opportunity, remaining uncertainty and next proof for suppliers, partners and long-duration capital.S12S13S14S15S16S17S18
  5. The decisive test through the early 2030s is several successive units entering commercial operation while the older fleet is retained or replaced. That evidence would show whether broad support is becoming repeatable net capacity rather than a larger catalogue of targets and unfinished projects.S01S02S04S07S08
Chapter 01 · Why now

A real build cycle on an uneven map

The global nuclear renaissance is being built, but not evenly. Policy support is broad; construction is concentrated; repeat commercial delivery is proven in only a small number of programmes. On 12 July 2026, IAEA PRIS listed 77 reactors and 80.720 GWe of net capacity under construction, of which China held 37 reactors and 39.952 GWe—48.05% of units and 49.49% of capacity. That makes China the fleet-scale case. Much Western re-entry remains spread across restart, review, licence, finance and a small set of builds, so the useful question is which project has reached which evidence state.S01S05S06S12S13S14S15S16S17S18

Those 77 reactors matter. They are physical projects that have crossed PRIS’s construction-start threshold, not a list of speeches or aspirations. But the total is not a forecast of 77 completions. PRIS begins under-construction status at the first major placement of concrete and ends it at first grid connection. It then calls a reactor operational from first grid, even when the period before declared commercial operation is still trial operation. A large live stock therefore proves that construction is under way. It says nothing by itself about when each unit will connect, when it will enter commercial service, how much older capacity will retire, or whether a programme can repeat the result.S01S02

The policy map is wider still. The IEA found support for expanding nuclear power in more than 40 countries, while the July 2026 PRIS construction table covered a much smaller set. National instruments also speak in unlike measures: the United States set a 400 GWe objective for 2050, the United Kingdom an ambition of up to 24 GWe by 2050, India a 100 GWe target for 2047, and Japan an outlook of approximately 20% nuclear generation in fiscal 2040. These are signals of direction, not quantities that can be added or translated into an implied reactor order. Every named project must still cross its own review, licensing, finance, construction and operating milestones.S01S06S26S27S28S29

This distinction changes the decision in front of a utility partner, supplier, lender or public authority. The decision-relevant unit is not a country headline or even a reactor name in a database. It is the latest achieved stage, the evidence that supports it and the next missing proof. The argument follows five steps: the live construction stock is real and concentrated; status is not a capacity forecast; serial delivery is the strategic advantage; fleet retention alters the net-capacity result; and the decisive proof in the 2030s will be successive units entering commercial operation. That sequence identifies which programme merits pursuit or deeper diligence now, and which still asks the reader to underwrite an announcement.S01S02S12S13S14S15S16S17S18S22

X01 From promise to power What does each evidence state prove, and what does it leave unproven?
01Policy or target
02Programme preparation
03Named proposal
04Regulator-accepted review
05Licence
06Finance or FID
07First major concrete
08First grid and trial
09Owner-declared commercial operation
10Successive commercial units
Official intent

Policy or target

An adopted ambition is not yet a named project.S26S27S28S29

Evidence boundaryStatus is stated from the cited public record.
Upstream

Programme preparation

Official roadmap and infrastructure work do not establish a reactor construction start.S01S30S36

Evidence boundaryStatus is stated from the cited public record.
Proposal

Named proposal

An official record identifies a project, but accepted regulatory review still requires separate evidence.S13S14

Evidence boundaryStatus is stated from the cited public record.
Review

Regulator-accepted review

A live review is evidence of process, not an issued licence.S13S14

Evidence boundaryStatus is stated from the cited public record.
Licensed

Licence

The exact permission and remaining control points matter; a site licence need not authorize nuclear construction.S14S15

Evidence boundaryStatus is stated from the cited public record.
Financed

Finance or FID

Capital commitment is consequential but does not substitute for first major concrete.S16

Evidence boundaryStatus is stated from the cited public record.
Under construction

First major concrete

PRIS construction status begins with first major concrete for the reactor-building base mat.S02

Evidence boundaryStatus is stated from the cited public record.
Connected / trial

First grid and trial

PRIS now calls the unit operational, but the declared commercial date can still be later.S02S18S32S33

Evidence boundaryStatus is stated from the cited public record.
Commercial

Owner-declared commercial operation

A dated authorised-owner declaration establishes commercial operation.S22

Evidence boundaryStatus is stated from the cited public record.
Repeat delivery

Successive commercial units

Several completed units show a delivery system continuing beyond one completion.S09S22

Evidence boundaryStatus is stated from the cited public record.
Definitions and scope. PRIS construction begins at first major concrete and its operational status begins at first grid. · Finance is shown separately because it is a capital milestone rather than a PRIS lifecycle state. S01S02S09S13S14S15S16S18S22S26S27S28S29S30S32S33S36What this establishes. Each stage retires one uncertainty; none can be promoted into the next stage without its own dated public record.
Chapter 02 · The long arc

Two build cycles and a long low-start interval

The present cycle is easier to understand against the first one. IAEA’s historical series records 305 construction starts totalling 264.128 GWe net during the 1970s. The annual high was 43 starts in 1976. First-grid connections peaked later, tying at 33 units in both 1984 and 1985; the 1985 cohort carried the higher capacity total, at 31.129 GWe net. That sequence does not prove one simple cause, but it shows the temporal shape of a build wave. Starts come first; grid connections arrive years later; commercial declarations can follow later again. Today’s policy and construction figures sit at different points on that same chain and should not be read as simultaneous output.S02S03

The earlier scale-up was not merely a set of reactor decisions. It depended on owners able to carry long projects, regulators able to license and oversee them, financing structures that could sustain construction, industrial supply chains that could make nuclear-grade systems, and a workforce able to repeat specialised work. The institutional point remains current. The IAEA’s Milestones Approach describes a nuclear programme as a system that also includes safety, security, safeguards, radioactive-waste management, legal and regulatory frameworks, human resources and decommissioning. Civil nuclear capacity is therefore not only an industrial-output question, and an increase in construction volume does not remove those continuing obligations.S03S30

After the first surge came a much quieter period. From 1988 through 2007, annual global construction starts never exceeded seven. Yet the interval still contained 73 starts and 61.505 GWe net. Pause is therefore too absolute. The more accurate description is a 20-year low-start interval: activity thinned sharply in aggregate while programmes in parts of Asia continued. That distinction matters because the capabilities inherited by countries were uneven. Some maintained active construction and regulatory pipelines; many advanced economies carried operating fleets forward while new-build experience became intermittent. The current re-entry challenge is partly the attempt to rebuild that delivery system while replacing or extending an ageing fleet.S03S04S06

The geography shifted further after 2010. The IEA’s 2025 review counted 52 reactor construction starts since 2017, of which 25 used Chinese designs and 23 Russian designs. Its later global review reported ten construction starts totalling 12.2 GW in 2025: nine in China and one in Russia. It also said that 94% of starts over the preceding decade used Chinese or Russian designs. These are measures of design origin and start location, not full attributions of ownership, finance or every supplier. Even with that boundary, they show why the contemporary cycle is different from a broad return to the old Western build map. The centre of active repetition has moved.S05S06

The most recent complete annual IAEA series records nine construction starts and six first-grid connections in 2024. The IEA then records ten starts in 2025. These adjacent figures are evidence of continuing activity, but they remain modest beside the 1970s peak and should not be merged into a forecast. They also capture different milestones: a start is first major concrete, while a grid connection marks the beginning of the PRIS operational state and may precede commercial operation. The current cycle becomes a renaissance in the stronger sense only if the start cohort moves through trial into commercial service and is followed by later units, rather than accumulating as a long-lived construction stock.S02S03S05

X02 Two build cycles, one long pause When did global construction starts and first-grid connections crest, thin and return?

Construction starts

average reactor construction starts per yearConstruction startsAll plotted rates are historical estimates derived from the complete published series and aggregated into complete periods on a common annual-average basis. First grid begins the PRIS operational state but is not a commercial-operation declaration; the current live stock is shown in the report opening.11.0/yr1954–1969HISTORICAL_ESTIMATE30.5/yr1970–1979HISTORICAL_ESTIMATE15.4/yr1980–1987HISTORICAL_ESTIMATE3.7/yr1988–2007HISTORICAL_ESTIMATE7.8/yr2008–2017HISTORICAL_ESTIMATE6.9/yr2018–2024HISTORICAL_ESTIMATE

First-grid connections

average first-grid connections per yearFirst-grid connectionsAll plotted rates are historical estimates derived from the complete published series and aggregated into complete periods on a common annual-average basis. First grid begins the PRIS operational state but is not a commercial-operation declaration; the current live stock is shown in the report opening.5.3/yr1954–1969HISTORICAL_ESTIMATE16.3/yr1970–1979HISTORICAL_ESTIMATE25.1/yr1980–1987HISTORICAL_ESTIMATE5.7/yr1988–2007HISTORICAL_ESTIMATE4.9/yr2008–2017HISTORICAL_ESTIMATE6.1/yr2018–2024HISTORICAL_ESTIMATE
All plotted rates are historical estimates derived from the complete published series and aggregated into complete periods on a common annual-average basis. First grid begins the PRIS operational state but is not a commercial-operation declaration; the current live stock is shown in the report opening.
Definitions and scope. Construction start means the first major placement of concrete under the PRIS definition. · First-grid connection begins the PRIS operational state but is not the commercial-operation date. S03What this establishes. Construction starts crested first; first-grid connections crested later, and both series then moved into a much lower-volume era.
Chapter 03 · The physical system

Status discipline reveals where scale actually sits

The first change is a stricter evidence ladder. Policy or target establishes direction. A named proposal establishes that an official body or authorised owner has identified a project. Regulator-accepted review establishes a live application, not a licence. A licence establishes a defined permission, often with conditions and regulatory control points. Finance or final investment decision shows capital commitment, but it does not substitute for construction authority. First major concrete establishes the PRIS construction start. First grid establishes connection and begins the PRIS operational state. Trial operation sits between first grid and declared commercial operation. A later unit reaching commercial operation begins to demonstrate repeat delivery. The order can overlap in practice, but no stage is evidence of the next.S02S14S15S16

China’s own records illustrate why these distinctions are substantive rather than semantic. At the end of May 2026, the national regulator reported 37 construction-licensed units and another 11 approved units awaiting construction. A paired licence for Xuwei Units 1 and 2 released the first-concrete control point for Unit 1 while retaining it for Unit 2. PRIS recorded Unit 1 entering construction four days later; Unit 2 had no construction-start row at the 12 July cut-off. The absence of that row is not evidence of cancellation. It shows that approval, a paired construction licence, release of a unit-specific regulatory control point and first concrete are different achieved states even inside a serial-build system.S01S09S10S11

The second change is concentration at both project and design level. China accounts for roughly half of the live PRIS construction stock by unit count and net capacity. The IEA’s recent-start record is also dominated by Chinese and Russian designs. This does not mean every project has the same delivery condition, nor that design origin identifies the full supply chain. It does mean that broad interest elsewhere has not yet produced an equally broad construction map. When a buyer asks where repeatable near-term demand may exist, the live evidence points first to programmes already licensing, pouring first concrete and advancing multiple units, not simply to jurisdictions with large 2050 ambitions.S01S05S06

The third change is the strategic meaning of repetition. A transparent sample of 12 completed units across five site programmes—Fuqing, Fangchenggang, Taishan, Sanmen and Barakah—contains seven same-site successors. Only two of those successors reached commercial operation faster than the selected first unit at their site. Construction-to-commercial durations in the sample range from 68.8 months for Fuqing 5 to 113.1 months for Sanmen 1. The sample is too small and varied to estimate a universal learning rate, and it contains no cost evidence. It shows something more useful: repetition creates programme continuity and reusable institutions, but the label repeat unit does not guarantee monotonically shorter elapsed time.S03S09S22

X03 Repeat delivery changes the record Do completed same-site successor units reliably take less time to reach commercial operation?
Fuqing 5China · HISTORICAL_ESTIMATE
68.8 months
HPR1000 design first-of-a-kind and first selected site unit.S09
Fangchenggang 3China · HISTORICAL_ESTIMATE
87.0 months
First selected unit at the site; not the design first-of-a-kind.S09
Taishan 1China · HISTORICAL_ESTIMATE
108.8 months
Commercial first-of-a-kind EPR and first selected site unit.S03S09
Sanmen 1China · HISTORICAL_ESTIMATE
113.1 months
Commercial first-of-a-kind AP1000 and first selected site unit.S03S09
Barakah 1United Arab Emirates · HISTORICAL_ESTIMATE
104.4 months
First national and site unit; not the APR1400 design first-of-a-kind.S03S22
Fuqing 6China · HISTORICAL_ESTIMATE
75.1 months
Same-site successor.S09
Fangchenggang 4China · HISTORICAL_ESTIMATE
89.0 months
Same-site successor.S09
Taishan 2China · HISTORICAL_ESTIMATE
112.8 months
Same-site successor.S03S09
Sanmen 2China · HISTORICAL_ESTIMATE
106.7 months
Same-site successor that completed faster than the selected site baseline.S03S09
Barakah 2United Arab Emirates · HISTORICAL_ESTIMATE
107.3 months
Same-site successor.S03S22
Barakah 3United Arab Emirates · HISTORICAL_ESTIMATE
101.0 months
Same-site successor that completed faster than the selected site baseline.S03S22
Barakah 4United Arab Emirates · HISTORICAL_ESTIMATE
109.2 months
Same-site successor.S03S22
Definitions and scope. Duration runs from the PRIS construction-start date to the declared commercial-operation date. · Comparison baseline means the first selected completed unit at the site, not always the design first-of-a-kind. S03S09S22What this establishes. Repeat delivery documents programme continuity and reusable institutions; this sample does not show that every successor finishes faster.
Chapter 04 · The global map

Re-entry describes several unlike things

The United States and Canada show three distinct modes. Vogtle Unit 4 is a recent large-reactor completion, evidence that the United States can finish a modern new-build unit; it is not yet proof of a repeated multi-site programme. Palisades remained a restart project in licensing and environmental review at the cut-off. The rescission of earlier shutdown certifications did not itself authorize restart or establish output. At Darlington, the Canadian regulator had issued a construction licence for one BWRX-300 and the project had entered licensed SMR construction, while a separate future operating-licence process remained ahead. Completion, restart licensing and SMR construction are all forms of re-entry, but they retire different uncertainties.S12S13S14S31

The United Kingdom and France add finance and operating-status distinctions. Hinkley Point C remained under construction under regulatory oversight. Sizewell C had a nuclear site licence and a final investment decision, but the site licence did not permit nuclear-related construction; finance and construction therefore remained separate milestones. Flamanville 3 had connected to the grid and remained in start-up or testing without a public commercial-operation date at the cut-off. PRIS would call that unit operational from first grid, but the comparison must call it connected or in trial until an authorised commercial declaration appears. These cases are not weak because their labels are precise. The precision tells a buyer which work is real and what proof is still missing.S02S15S16S17S18S32S33

Japan and Korea demonstrate a different split between fleet restoration and new-build continuation. Onagawa Unit 2 completed a regulated restart into commercial operation. That is meaningful retained capacity, but it is not a new-build completion. Saeul Unit 3 had an operating licence and public start-up generation evidence while still lacking an achieved commercial declaration at the cut-off. An operating licence authorizes a stage; observed generation shows connection or trial; neither should be promoted into the owner’s later commercial milestone. For a market participant, opportunities around restart, commissioning and new construction may overlap, but the delivery evidence and risk still differ.S19S20S34S35

India separates an achieved cohort from a long-range target. Kaiga Units 5 and 6 reached first concrete as the first project in a sanctioned fleet-mode cohort. That is materially stronger evidence than the national objective of 100 GWe by 2047, but it does not convert the whole objective into financed or licensed units. The useful diligence question is what follows Kaiga: whether subsequent units in the sanctioned cohort pass their own permissions, funding and construction-start milestones. Treating the target as a build count would hide the difference between a policy direction and the actual throughput of India’s delivery system.S21S28

Newcomer programmes show how far apart nominally similar national stories can be. The United Arab Emirates completed commercial operation of the four-unit Barakah programme. Turkiye remained in construction and commissioning at Akkuyu; fuel delivery or a target for first electricity did not establish grid connection. Egypt had all four El Dabaa units under construction without achieved grid dates. The Philippines remained further upstream: its government had adopted a nuclear-energy roadmap and was developing national infrastructure, but it had no reactor in the July PRIS construction set. These are programme completion, active construction or commissioning, multi-unit construction without connection, and policy or institutional preparation. They belong on one global map only if the map keeps their stages visible. The IAEA newcomer framework also makes clear that construction is not the whole national undertaking: regulatory independence, safety, security, safeguards, waste, human resources and decommissioning remain enduring responsibilities.S01S22S23S24S30S36

Latin America exposes a second distortion: equal unit counts can conceal profoundly unequal scale and condition. PRIS assigns one under-construction unit to Argentina’s CAREM25 prototype at 25 MWe net and one to Brazil’s Angra 3 at 1,340 MWe net, a 53.6-to-one capacity ratio. Neither had a recorded first-grid date. The administrative label is useful because it preserves a common lifecycle definition, but it is insufficient as a delivery judgement. A credible comparison must pair unit count with capacity, construction age, achieved milestones and current authoritative project evidence. One reactor is not one standard quantum of programme progress.S01S25

X04 Western re-entry is not one status Which evidence state has each selected Western re-entry case actually reached?
RecordStatusWhat the evidence says
Vogtle 4Commercial operationA recent large-reactor completion, but not a repeat multi-site build programme.S12S31
PalisadesRestart licensingReauthorization and environmental work remained active; the unit was not counted as restarted.S13
Darlington BWRX-300Under constructionA construction licence and physical construction, with regulatory control points and a separate future operating review.S14
Hinkley Point CUnder constructionActive large-reactor construction; component permissions do not establish connection or operation.S17
Sizewell CSite licence and FIDThe regulator states that the site licence does not itself permit nuclear-related construction.S15S16
Flamanville 3Connected / start-upFirst electricity had occurred, but no achieved public commercial date was used.S18S32S33
Onagawa 2Restarted commercial operationA regulated restart completion, not a new-build completion.S19
Saeul 3Licensed / start-upAn operating licence and trial-generation evidence did not establish the planned commercial date.S20S34S35
Definitions and scope. Cut-off status is the latest achieved authoritative milestone found by 13 July 2026. · Restart licensing, first grid, site licence, FID and commercial operation remain separate states. S12S13S14S15S16S17S18S19S20S31S32S33S34S35What this establishes. Western re-entry is visible, but its selected cases sit across several lifecycle states rather than one uniform new-build wave.
Chapter 05 · The constraint

The operating fleet changes the net result

New-build volume is only one side of the capacity equation. PRIS listed 417 operational reactors with 379.700 GWe net on 12 July 2026. Of that fleet, 283 reactors and 256.719 GWe were at least 30 years from first grid; 207 reactors and 182.478 GWe were at least 40 years; and 50 reactors and 38.550 GWe were at least 50 years. These are nested cohorts, not quantities to add. Age is not a retirement forecast, licence expiry, generation measure or safety judgement. It is evidence that a large share of the fleet will require continuing owner, regulator and investment decisions while new projects advance.S04

Life extension can therefore affect the capacity outcome as much as construction. The IEA reported more than 60 reactor life-extension decisions in the five years preceding its 2025 report, covering nearly 15% of the global fleet. Separately, the OECD NEA Low Scenario expects more than 50 GWe to retire by 2040, while its Current Trends Scenario expects 10 GWe as long-term operation and investment retain more capacity. Those are conditional model outputs, not predictions of individual reactor closure. A life-extension decision is not a guarantee of extra operating years either: inspections, refurbishment, licensing and owner economics still intervene. The contrast shows why an outlook cannot subtract assumed retirements mechanically or treat all older reactors as fixed future capacity. The net path is the result of commercial additions, permanent shutdowns, restarts and authorised continued operation, each on its own evidence trail.S04S06S07

The same bottleneck applies to future scenarios. The OECD NEA’s 2050 cases reach 347 GWe in Low, 619 GWe in Current Trends, 883 GWe in Ambitious and 1,324 GWe in Transformative. Only the Transformative case exceeds the tripling objective. These are conditional modelled outcomes, not forecasts. The higher cases depend on linked changes in project execution, industrial capability, workforce, supply chains, investment frameworks and finance, together with long-term operation and new build. The capacity endpoints cannot be detached from the delivery systems assumed to produce them.S07S08

That is the practical bottleneck: conversion. More policy support can widen the top of the funnel, but it cannot by itself supply qualified people, regulator capacity, repeat orders, finance structures or commercial completions. An announcement-heavy pipeline can coexist with a concentrated build map and an ageing operating base. The programmes most likely to matter to a buyer are those that can show both sides of the equation: a credible route through the next project milestone and a realistic account of fleet retention or replacement. The gap between 619 GWe and 1,324 GWe is not a difference in optimism. It represents a much more demanding execution system.S04S06S07S08S13

X05 The existing fleet counterweight How large is the operating-fleet counterweight beside the live new-build stock?

Net electrical capacity

GWe net operationalNet electrical capacityObserved fleet and construction records are administrative PRIS values; retirement exposure is modelled. The age cohorts are nested and must not be added together. Age is not licence expiry or retirement, under-construction capacity is not guaranteed future commercial capacity, and modelled retirement exposure is not added to observed age.379.700 GWe12 Jul 2026ADMINISTRATIVE256.719 GWe12 Jul 2026ADMINISTRATIVE182.478 GWe12 Jul 2026ADMINISTRATIVE38.550 GWe12 Jul 2026ADMINISTRATIVE80.720 GWe12 Jul 2026ADMINISTRATIVE

Conditional retirement exposure

GWe modelled retirement exposureConditional retirement exposureObserved fleet and construction records are administrative PRIS values; retirement exposure is modelled. The age cohorts are nested and must not be added together. Age is not licence expiry or retirement, under-construction capacity is not guaranteed future commercial capacity, and modelled retirement exposure is not added to observed age.more than 50 GWeLow · by 2040MODELLED10 GWeCurrent Trends · by 2040MODELLED
Observed fleet and construction records are administrative PRIS values; retirement exposure is modelled. The age cohorts are nested and must not be added together. Age is not licence expiry or retirement, under-construction capacity is not guaranteed future commercial capacity, and modelled retirement exposure is not added to observed age.
Definitions and scope. Observed fleet values use PRIS reference-unit net electrical capacity in GWe. · The age cohorts are nested; NEA scenario retirement figures are conditional model outputs and are not added to observed age. S01S04S07What this establishes. The live build is substantial, but the net capacity result also depends on fleet retention; the NEA retirement exposure changes materially between its Low and Current Trends cases.
X07 Tripling is a condition, not a forecast What 2050 capacity does each NEA case produce, and what delivery system does it assume?
LowWorld · MODELLED
347 GWe
Minimal investment and retirements without substantial replacement.S07S08
Current TrendsWorld · MODELLED
619 GWe
Present policies and investment, with modest growth supported by long-term operation.S07S08
AmbitiousWorld · MODELLED
883 GWe
Accelerated support and investment with a larger contribution from conventional and small modular reactors.S07S08
TransformativeWorld · MODELLED
1,324 GWe
Successful long-term operation, accelerated large build, significant SMRs and a step change in execution, industry and finance.S07S08
Definitions and scope. Each bar is a conditional modelled 2050 capacity case, not a forecast. · Only the Transformative case exceeds the tripling objective under its stated delivery assumptions. S07S08What this establishes. Tripling is the output of the most demanding delivery assumptions, not the base result implied by broad policy support.
Chapter 06 · What to watch

Four tests over the next five years

The next 60 months should be read as a sequence of achieved proofs, not as a race between target totals. Four signals would show whether construction is broadening beyond its present concentration and whether re-entry is becoming a repeatable delivery system. Each signal has a public evidence owner and a condition that would materially change the answer.S01S02S24S25

Taken together, the signals create a usable scorecard. First concrete tests whether policy and finance are converting. Commercial operation tests whether construction is completing. A repeat unit tests whether delivery is becoming institutional rather than exceptional. Net capacity tests whether new build is outrunning loss from the existing fleet. The buyer should ask for the next dated record in that chain, identify who must issue it and decide what evidence would stop the commitment. Evidence-state discipline is more demanding than counting announcements, but it is also more actionable: it shows where a project can still fail to prove its case.S01S02S04S07S08S25

X06 The proof moves from contracts to operating load Which records should a buyer check over the next five years?
Evidence and owner
Now12m24m36m60m
Test that would change the judgement
Now–18 months

Stage conversion in live Western cases

Who can evidence it: National regulators and authorised project owners

Regulator or owner records moving restart, construction and connected start-up cases into their next achieved state would show that heterogeneous re-entry is progressing rather than remaining static.S13S14S18S20

Now18m
Would change the judgementThe concentration thesis weakens if several Western cases convert cleanly into authorised operation or commercial service on their disclosed paths.
6–36 months

Licence and FID convert into repeat first concrete

Who can evidence it: Regulators, governments and project companies

Several second or subsequent units moving into recognized construction would show that permissions, teams and supply chains are carrying beyond isolated first projects.S02S14S15S16S17

6m36m
Would change the judgementThe thesis weakens if several Western programmes reach repeat first concrete and the distribution of new starts shifts durably away from China.
12–48 months

Successive units reach commercial operation

Who can evidence it: Authorised owners and national regulators

Dated handovers of second and later units are the clearest test that a programme is repeating delivery, while exact first-grid dates preserve the intervening trial stage.S02S03S09S22

12m48m
Would change the judgementThe thesis weakens if successors complete more predictably across several programmes and commercial additions broaden beyond today’s concentrated set.
Now–60 months

Net additions survive fleet-retention decisions

Who can evidence it: Fleet operators and national regulators

Commercial additions, permanent shutdowns, restarts and authorised long-term operation together determine whether gross construction becomes durable net capacity.S04S06

Now60m
Would change the judgementThe capacity constraint weakens if commercial additions rise across regions without an offsetting retirement problem and life-extension decisions become continued licensed operation.
Definitions and scope. The range bars are monitoring windows, not forecast completion dates. · Operating load is the lagging test; agreements, funding and orders are earlier evidence. S13S14S18S20S02S15S16S17S03S09S22S04S06What this establishes. Evidence should progress from agreements and cost allocation to equipment, construction and energised load.
Conclusion

Separate the opportunity from the announcement

The global nuclear renaissance is real, but its strongest evidence is not the breadth of national ambition. It is the smaller map of first concrete, connection, commercial operation and repeated delivery. China holds roughly half of the dated PRIS construction stock by units and net capacity and continues to build at fleet scale. Elsewhere, re-entry is consequential but mixed: recent completion, restart, first SMR construction, active large-reactor builds, finance decisions and connected trial units all matter, yet they are not the same proof.S01S05S12S13S14S16S17S18

The commercial question is therefore sharper than which country supports nuclear. Ask which named programme has reached an achieved stage, which body confirms it, what the next dated milestone is and whether a later unit is following. Then place that project beside the existing-fleet decision: life extension, restart, permanent shutdown or replacement. That method exposes both opportunity and missing evidence before teams, partnerships, manufacturing capacity or long-duration capital are committed.S02S04S06S25

The strongest confirming signal through the early 2030s will be successive units entering commercial operation across more programmes, supported by repeat first concrete and a stable net fleet. The answer would change if those completions broaden geographically and become more predictable; it would harden if policy remains widespread while construction and repeat commercial delivery stay concentrated. Name the country, project, supplier decision or capacity claim, then test it against policy, review, licence, finance, construction, connection and commercial-operation evidence. The access route below turns that question into a scoping note: the three public facts that would move the decision forward, and the evidence gap that should stop it before deeper diligence.S01S02S07S08S24S25

Follow the next achieved milestone and the next commercial unit—not the largest announcement.

Evidence · definitions · limits

Every consequential claim can be checked.

The evidence is open. Plans, scenarios and operating facts remain visibly different.

The evidence cut-off is 13 July 2026. Construction and fleet counts use dated IAEA PRIS administrative snapshots; historical starts and first grids use the IAEA’s 2025 reference series; scenarios retain the NEA’s source-native labels and are not forecasts. The NEA values shown here use 347, 619, 883 and 1,324 GWe because the release, executive summary and numeric table agree; conflicting stale prose in the report is not used. Project stages come from regulators, governments or authorised owners, and every first-grid record remains separate from commercial operation. Policy instruments remain unscaled because capacity, generation share and target years are not interchangeable.S01S02S03S04S07S08S12S13S14S15S16S17S18S19S20S21S22S23S24S25S26S27S28S29S31S32S33S34S35S36

This is a public-source comparison of programme and project evidence, not an assessment that any plant, design or project is safe, licensed to a future stage, financeable or suitable for procurement. It excludes sensitive physical-security, safeguards, cyber, site-layout, transport and route detail. Safety, security, safeguards, radioactive-waste management, decommissioning and regulatory obligations continue throughout a programme and cannot be inferred from construction speed. Public records also cannot establish non-public contract performance, full supplier readiness or future regulatory outcomes. The analysis supports stage discipline and relative programme evidence; it does not provide investment, legal, safety, licensing or procurement advice.S02S14S15S20S30

  • PRIS is live, so counts and statuses are a dated 12 July 2026 administrative snapshot rather than a schedule or completion forecast.
  • The completed-unit duration sample is transparent but selected; it cannot estimate a universal learning rate, cost effect or schedule probability.
  • Fleet age is not retirement timing, licence expiry, availability or safety performance, and the displayed age cohorts are nested rather than additive.
  • Public records cannot establish non-public contract performance, complete supplier readiness, future regulatory outcomes or project economics.
  • The report excludes sensitive physical-security, safeguards, cyber, site-layout, transport, route and exploitable supplier detail.
Filter by evidence role
S01International Atomic Energy Agency, Power Reactor Information SystemReactors under construction by country · database update 2026-07-12Dated global and Chinese unit counts and reference-unit net capacity under construction
S02International Atomic Energy Agency, Power Reactor Information SystemPRIS glossary · retrieved 2026-07-13Construction start, under construction, first grid, trial operation and commercial-operation definitions
S03International Atomic Energy AgencyNuclear Power Reactors in the World, 2025 Edition · 2025Historical annual construction starts, first-grid connections, duration cohorts and unit milestone dates
S04International Atomic Energy Agency, Power Reactor Information SystemOperational reactors by age · database update 2026-07-12Current operational fleet and nested age cohorts by unit and net capacity
S05International Energy AgencyGlobal Energy Review 2026: Technology — Nuclear · 2026Construction starts and design concentration through 2025
S06International Energy AgencyThe Path to a New Era for Nuclear Energy — Executive Summary · 2025-01-16Policy breadth, construction-design concentration, fleet age and life-extension decisions
S07OECD Nuclear Energy AgencyNuclear Energy Outlook: Global Installed Capacity to 2050 and Beyond · 2026-07-02Four 2050 capacity scenarios and their delivery, industrial, workforce and finance conditions
S08OECD Nuclear Energy AgencyMeeting the moment: New NEA analysis highlights the scale of the challenge · 2026-07-02A second official NEA locator for the scenario values and tripling condition
S09International Atomic Energy Agency, Power Reactor Information SystemChina country details and reactor records · database update 2026-07-12Chinese construction and completed-unit milestone dates
S10National Nuclear Safety Administration of ChinaNuclear-power regulatory overview · status at end-May 2026Staged licensing and separate construction-licensed and approved-awaiting-construction states
S11Ministry of Ecology and Environment of ChinaXuwei Units 1 and 2 construction-licence decision · 2026-01-12Unit-specific release and retention of the first-concrete control point
S12U.S. Nuclear Regulatory CommissionVogtle Unit 4 · retrieved 2026-07-13Recent US large-reactor licensing and completion sequence
S13U.S. Nuclear Regulatory CommissionPalisades Nuclear Plant · retrieved 2026-07-13Restart reauthorization, licensing and environmental-review status
S14Canadian Nuclear Safety CommissionDarlington New Nuclear Project · retrieved 2026-07-13BWRX-300 construction licence, current construction and regulatory control points
S15UK Office for Nuclear RegulationONR grants nuclear site licence for Sizewell C · 2024-05-07Site licence and its explicit non-authorisation of nuclear construction
S16UK GovernmentSizewell C gets green light with final investment decision · 2025-07-22Final investment decision and disclosed financing stage
S17UK Office for Nuclear RegulationHinkley Point C · retrieved 2026-07-13Licence, FID, first nuclear-safety concrete and active construction status
S18Electricite de FranceFlamanville EPR produces first electricity on the national grid · 2024-12-21First grid connection without a commercial-operation claim
S19Tohoku Electric Power CompanyCommencement of commercial operation of Onagawa Unit 2 · 2024-12-26Commercial restart after pre-service inspection
S20Nuclear Safety and Security Commission, Republic of KoreaOperating licence approved for Saeul Unit 3 · 2025-12-30Operating licence as a distinct milestone before commercial operation
S21Nuclear Power Corporation of India and Press Information BureauFirst pour of concrete for Kaiga Units 5 and 6 · 2026-03-01First concrete and the sanctioned ten-unit fleet-mode cohort
S22Emirates Nuclear Energy CorporationBarakah programme completion statement · retrieved 2026-07-13All four Barakah units commercially operational and repeat-unit comparison context
S23Ministry of Energy and Natural Resources, TurkiyeAkkuyu Nuclear Power Plant Project · retrieved 2026-07-13Construction chronology and commissioning-stage boundary
S24Nuclear Power Plants Authority, EgyptFirst concrete for El Dabaa Unit 4 · 2024-01-23All four El Dabaa units reaching construction status
S25Comision Nacional de Energia Atomica, ArgentinaCAREM project · retrieved 2026-07-13Prototype character, construction condition and domestic capacity convention
S26President of the United StatesExecutive Order 14300 — Ordering the Reform of the Nuclear Regulatory Commission · 2025-05-23United States 2050 nuclear-capacity objective
S27UK Government, Department for Energy Security and Net ZeroCivil Nuclear: Roadmap to 2050 · 2024-01-11United Kingdom 2050 nuclear-capacity ambition
S28Government of India, Ministry of Finance and Press Information BureauNuclear Energy Mission for Viksit Bharat · 2025-02-01India 2047 national nuclear-capacity policy target
S29Cabinet of Japan and Agency for Natural Resources and EnergySeventh Strategic Energy Plan · Cabinet decision 2025-02-18Japan FY2040 nuclear generation-share outlook
S30International Atomic Energy AgencyMilestones Approach · 2015Safety, security, safeguards, waste, legal, regulatory, workforce and decommissioning infrastructure boundaries
S31Georgia PowerVogtle Unit 4 enters commercial operation · 2024-04-29Dated owner declaration of Vogtle Unit 4 commercial operation
S32International Atomic Energy Agency, Power Reactor Information SystemFlamanville 3 reactor details · database update 2026-07-09Flamanville first-grid date and commercial-operation date recorded as not available
S33Electricite de FranceFlamanville 3 project page · retrieved 2026-07-13Flamanville current start-up and testing status at the evidence cut-off
S34Korea Hydro and Nuclear PowerSaeul Units 3 and 4 · status at 2026-03-31Saeul project milestones and planned rather than achieved commercial dates
S35Korea Hydro and Nuclear PowerSaeul real-time power output · page timestamp 2026-07-10Saeul 3 start-up generation evidence before commercial declaration
S36Department of Energy, Republic of the PhilippinesPhilippines unveils nuclear energy roadmap · 2024-09-25Official newcomer roadmap and infrastructure work without a PRIS construction project
Showing 36 of 36 sources
Questions readers ask
Is a global nuclear renaissance actually under construction?

Yes, but the live construction map is concentrated. Policy support and project proposals cover a much wider set of countries.

How much of current construction is in China?

IAEA PRIS listed China at roughly half of global reactors and net capacity under construction on 12 July 2026.

What separates a proposal from an operating reactor?

Review, licence, finance, first major concrete, grid connection, trial operation and commercial operation are separate dated evidence states.

Does this report assess nuclear safety or site security?

No safety assurance is offered. The report uses public regulatory and project status while excluding sensitive security, safeguards, cyber and route detail.

Use the report

Separate one nuclear opportunity from an announcement.

Name a country, project, supplier decision or capacity claim. Lansary will separate policy, review, licence, finance, construction, connection and commercial-operation evidence.

Test a nuclear opportunity